Sayfa 212III. Unforeseen Physical Risks – Man-Made Conditions: Case Study #2-The Incomplete Employer’s Input Data
This case study relates to the construction of a wind farm. The contract was a design-build…
The tender documents, which were of course an integral part of the contract documents,…
It later transpired that the local authorities had planned the construction of a…
The issues that arose as a consequence of these developments were thus the follo…
Should the contractor have questioned the Employer’s Input Data and/or investigated…
Should the contractor have examined the local zoning and development plans to see…
We will revisit these issues below, when addressing due diligence matters.…