IV. Unforeseen LEGAL Risks: Case Study #3-The Slow-Moving Customs Processes
This case concerns the construction of a water desalinisation plant in a North-African…
At the time the contract was entered into, the pace of customs clearance in the country…
The unintended result of this directive was a significant increase in the time needed…
What is interesting in this case is that there was no change to the law itself: the…