B. Acceleration Claims
To simplify, an acceleration claim is a claim made by the contractor when either…
■ The employer instructs the contractor to complete the works in advance of the agreed…
■ The contractor would be entitled to an extension of time but this extension is…
In these cases, it is generally recognised that the contractor is entitled to the…
Acceleration claims are notoriously difficult to quantify and to prove. Even where…
In case of constructive acceleration, the contractor’s task becomes even more difficult.…