Sayfa 1105.2.1.2.2. Sub-clause 15.2.(b) – intention not to continue to performance
This clause sets forth a general ground entitling the employer to terminate the contract.…
The contractor’s abandonment is observable however what action may set forth the…
‘Intention not to continue the performance’ is similar to term ‘repudiation’ in common…
This clause of the FIDIC contracts can be liken to the application of Article 124…
5.2.1.2.1. Sub-clause 15.2.(a) – combining clause of notice to correct to the grounds
5.2.1.2.3. Sub-clause 15.2.(c) – delays and impediments of the contractor and non – fulfilment of the correction of the defects