Figure 3: CPM schedule for the simple example projectSayfa 236…
The chart at Figure 3: CPM schedule for the simple example project shows the planned…
The critical path consists of the tasks whose sequence and timing determine the overall…
By inspection of the chart at Figure 3: CPM schedule for the simple example project…
Due to the varying duration of similar tasks in each building, after site establishment,…
■ Building 1: Foundations then Walls; then…
■ Building 2: Walls then Roof; then…
■ Building 3: Roof through to Handover; then…
■ Demobilisation and project Completion.…
A key point to note is that demobilisation (ID 28), i.e. removal from site of the…
I have marked the as-built critical path thus assessed with a red line on the chart…
Figure 4: As-built critical path for the simple example project Being based on interpretation of the facts and on analysis of the schedule, the as-built…
■ Building 1: Foundations then Walls; then…
■ Building 2: Walls; then…
■ Building 3: Walls then Roof; then…
■ Building 1: Roof through to Handover; then…
■ Demobilisation and project Completion.…
It can be seen by comparison of the baseline and as-built critical paths that the…
To confirm this, the expert may check the planned float and the as-built delay to…
Comparison of the baseline and as-built dates for handover of Building 1 as shown…
Accordingly, in respect of time, the expert has explained “why” project completion…