- Pocerady lignite-fired power plant (1 000 MW); orSayfa 185…
- Chvaletice lignite-fired power plant (800 MW); or…
- Detmarovice coal-fired power plant (800 MW), or…
- Melnik III lignite-fired power plant (500 MW) and Tisova lignite-fired power plants…
CEZ agreed not to acquire direct or indirect influence over the divested generation…
The observations received in response to the market test notice of the Commission,…
The commitments in their final form satisfied the Commission. The transfer of some…
The former Commission Vice-President responsible for competition policy, Joaquin…
In order to assess the necessity and sufficiency of the commitments implemented by…
Nevertheless, it is difficult to state that the imposition of structural commitments…
To sum up, the CEZ decision of the Commission can be seen as another attempt to remove…