C. United States
As a general proposition,(27) in the United States, where concurrent delay arises, the contractor is entitled to an extension of time for the full period of concurrent delay (and so the employer is not entitled to liquidated damages), but the contractor is not entitled to prolongation costs - i.e. time but not money.(28)…